Project Description

Scope of Work: 6th Floor Abseil Glass Replacement
Mode of Access: Rope Access, Internal Team
Location: Edinburgh, Scotland
Team Size: 5
Duration: 1 Shift

Glazing Rope Access Scottish based team completed 6th floor glass unit replacement to a high-rise office block located in central Edinburgh.

Due to the sites location and height, reaching the damaged unit required the use of an abseil team. We provided a team of IRATA trained abseilers and internal glazing operatives to conduct the required high level glass unit replacement. After initial site survey, our operatives decided to conduct the operation out of hours to reduce disruption to the building’s occupants.

After removing the damaged glazed unit, our team then cleaned the aperture ready for the installation of the replacement unit. Our team safely conducted the installation of the new unit before clean down and handover back to the client.