Project Description
Scope of Work: Replacement of Curtain Wall Glazing
Mode of Access: Abseil, City Crane, Onsite Cradle System
Location: London
Team Size: 12
Duration: 4 Weeks
This high rise commercial building required multiple glass replacements. Due to the site’s difficult access, the team mobilised onsite using a combination of city cranes, rope access and the onsite cradle system to provide a safe method of work when conducting the required glass replacements.
The rare specification of glass resulted in our procurement team sourcing from a European glass processing plant and our logistics team ensured the delivery coincided with our mobilisation to reduce the works duration.