Project Description
Scope of Work: Overhead Glazed Dome Refurbishment
Mode of Access: IRATA Trained Abseil Team
Location: Cumbria
Team Size: 12
Duration: 16 Weeks
Glazing Rope Access complete phased refurbishment works to large centrally glazed overhead dome units for a nationwide Holiday Park client.
As part of our overall package, we completed a sample bay of works showing the client our safe method of work and the installed of upgraded components.
With the sample bay passing the rigorous testing required by the client, our team moved onto repeat the process for the whole structure.
Utilising our vast experience in commercial glazing and our IRATA trained rope access technicians enable us to complete the works of upgrading the system components to programme and on budget.